Back to all reports

Unfinished works

Reported via iOS in the Road and Pavement Issues category by Mark Painter at 14:02, Monday 7 January 2019

Sent to Bromley Council 3 minutes later

The pavement and junction works were finished a month ago, yet this element still remains and the barriers keep falling down, making the problem worse

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 14:10, Monday 7 January 2019

  • Our contractor has informed us that the feeder pillar is due to be disconnected by UKPN next week which will allow the paving works to be completed - apologies for the delay

    Posted anonymously at 11:27, Tuesday 29 January 2019

  • Still open, via questionnaire, 15:07, Monday 4 February 2019

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 07:08, Tuesday 12 February 2019

This report is now closed to updates. You can make a new report in the same location.