Closed
Surface damage
Reported via desktop in the Road, Pavement and PROW Issues category anonymously at 15:33, Thu 2 December 2021
Sent to Bromley Council less than a minute later. FixMyStreet ref: 3155748.
Large holes appearing round drain cover on kerb Biggin Hill bound. Please fill. Also various other holes opening up in this direction for next half mile, Please fix before they get worse.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council at 15:33, Thu 2 December 2021
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council at 12:16, Thu 9 December 2021
-
Almost a month and still no fix. There seems to be a real issue with the surface all the way from Leaves Green through to Westerham Hill where repairs don't last, and there seems to be a real reticence from all parties to do anything about it. The road surface resembles some sort of moonscape in some places, and I wish a few more of the good citizens of Biggin Hill would start to kick up a real stink about this! After all, it's your tyres and suspension too, before we start on the hazzard to cyclists!
Posted anonymously at 17:04, Thu 30 December 2021
Still open, via questionnaire -
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council at 10:45, Tue 11 January 2022
-
Road seems to be a big problem esp in the winter when huge holes appear all the way from Leaves Green through Biggin Hill out to Westerham Hill. It is difficult to safely negotiate these holes, which the council appear very slow to fix. And often the repairs don't last, or indeed the repair lasts, but the area round it then needs attention! A complete resurfacing job is no doubt out of the question on cost grounds.
Posted anonymously at 17:48, Thu 27 January 2022
Still open, via questionnaire -
The information supplied is insufficient to pinpoint the area of deterioration. Specific problems will be investigated with location details or they will be identified as part of the cycle of routine safety inspections of all publicly maintained highways to ensure that maintenance is undertaken as effectively and efficiently as possible.
State changed to: No further action
Posted by Bromley Council at 12:45, Wed 2 February 2022
This report is now closed to updates from the public. You can make a new report in the same location.