Fixed
Pot hole outside no.42 Ridgeway Drive.
Reported via mobile in the Road, Pavement and PROW Issues category anonymously at 09:02, Wednesday 12 January 2022
Sent to Bromley Council less than a minute later
Pothole appeared before Christmas -cracking up badly now.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 09:04, Wednesday 12 January 2022
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 16:29, Friday 14 January 2022
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 12:44, Monday 17 January 2022
-
The fix has not worked. It started to crack and today (Monday 17th) the pothole has re-emerged.
Posted anonymously at 12:54, Monday 17 January 2022
-
Our contractor has been notified to take the appropriate action.
State changed to: In progress
Posted by Bromley Council
at 12:51, Monday 24 January 2022
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 10:56, Monday 31 January 2022
-
Our contractor has been notified to take the appropriate action.
State changed to: In progress
Posted by Bromley Council
at 12:41, Tuesday 8 February 2022
-
We are continuing to investigate and working to resolve this report
Posted by Bromley Council
at 16:47, Tuesday 15 March 2022
-
The latest fix has worked. Thanks
State changed to: Fixed
Posted anonymously at 16:52, Tuesday 15 March 2022
-
Thank you for using FixMyStreet to report your concerns to Bromley.
Posted by Bromley Council
at 17:09, Tuesday 15 March 2022
-
The issue has been re-attended and additional works completed. If the issue re-occurs please re-report via: https://fix.bromley.gov.uk
Posted by Bromley Council
at 09:07, Saturday 19 March 2022