Fixed
SECOND REQUEST: ‘trench’ developing in centre of road
Reported via desktop in the Road, Pavement and PROW Issues category anonymously at 11:48, Sunday 16 January 2022
Sent to Bromley Council less than a minute later
As per previous report and attached photos taken 8am Sunday 16 January; potentially dangerous to (motor)cyclists....
Please can it be filled and made safe this time.....
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 11:49, Sunday 16 January 2022
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 10:54, Tuesday 18 January 2022
-
Still waiting; for a quiet time? Half term this week.....
Posted anonymously at 12:06, Sunday 13 February 2022
Still open, via questionnaire -
As outlined at: http://www.bromley.gov.uk/ fixservices please allow up to 35 days for remedial works to be undertaken.
Jobs to repair highway defects are raised on timescales according to the priority and risk of the defect. However, dependent upon the cause and nature of the issue time frames for a response can vary so please allow up to 35 calendar days for works to be undertaken. More information can be found on our Road and Pavement Defect Environmental Service Aims at: https://www.bromley.gov.uk/ info/ 200119/ customer_services/ 921/ environmental_services_aims/ 17
Posted by Bromley Council
at 17:14, Sunday 13 February 2022
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 12:08, Wednesday 16 February 2022
-
A great improvement to safety on this busy, arterial road, thank you.
Posted anonymously at 12:44, Sunday 13 March 2022