A bad pothole on the corner of Queensway/Tudor Way was given a temporary repair a few months ago, but this patch of road is still in a bad condition (very bumpy) and needs a permanent fix.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 15:25, Fri 22 July 2022
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 13:25, Thu 28 July 2022
-
It is now over 7 weeks since I reported this and it still has not been dealt with. What is the reason for the delay?
Posted anonymously at 17:05, Sat 10 September 2022
-
Thank you for your update, Further works raised remain outstanding with our contractor and is awaiting completion. We apologise for the delay.
Posted by Bromley Council
at 11:22, Mon 12 September 2022
-
Thank you for your update, Additional works have now been raised with our contractor to resurface the affected area reported and the is awaiting completion. We apologise for the delay and any inconvenience caused by this matter.
Posted by Bromley Council
at 12:46, Tue 4 October 2022
-
This matter is still outstanding and is now considerably outside your service timescale. When is it going to be dealt with? Is your contractor being penalised for their abysmal service?
Posted anonymously at 18:57, Sat 22 October 2022
-
For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake the works.
Posted by Bromley Council
at 08:20, Wed 26 October 2022
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 11:00, Tue 1 November 2022
-
Our contractor has been notified to take the appropriate action.
State changed to: In progress
Posted by Bromley Council
at 13:31, Friday 20 January 2023
-
Appropriate actions has been undertaken by our contractor to resolve this matter. We apologise for the delay.
State changed to: Closed
Posted by Bromley Council
at 13:42, Friday 27 January 2023
-
Thank you for using FixMyStreet to report your concerns to Bromley.
State changed to: Fixed
Posted by Bromley Council
at 13:42, Friday 27 January 2023