Fixed
Two holes
Reported via iOS in the Road Defect category anonymously at 13:45, Saturday 7 January 2023
Sent to Bromley Council less than a minute later. FixMyStreet ref: 4098198.
These hopes are still here causing a real hazard to cyclist
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 13:46, Saturday 7 January 2023
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 08:52, Wednesday 11 January 2023
-
The repairs have been programmed and will be carried out shortly. Thank you for your patience.
Posted by Bromley Council
at 12:33, Friday 17 February 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 14:34, Tuesday 21 February 2023
-
Our contractor has been notified to take the appropriate action.
State changed to: In progress
Posted by Bromley Council
at 16:08, Thursday 9 March 2023
-
Our contractor will be returning to complete the works to our satisfaction. Thank you for your patience.
Posted by Bromley Council
at 17:47, Thursday 16 March 2023
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 17:48, Thursday 16 March 2023
-
We are working with our Minor Works contractor to resolve some issues. Thank you for your patience.
Posted by Bromley Council
at 11:50, Thursday 23 March 2023
-
We are monitoring our contractor to ensure these works are completed. Thank you for your patience.
Posted by Bromley Council
at 17:16, Wednesday 29 March 2023
-
Our contractor will be attending shortly. Thank you for your patience.
Posted by Bromley Council
at 12:37, Thursday 30 March 2023
-
Thank you for your further comments regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able.
Posted by Bromley Council
at 18:39, Tuesday 4 April 2023
-
A job was raised yesterday to repair another area near the railway station. Thank you for your patience.
Posted by Bromley Council
at 11:40, Tuesday 18 April 2023
-
We are working with our contractor to ensure this work is completed. Thank you for your patience.
Posted by Bromley Council
at 18:42, Thursday 20 April 2023
-
I have contacted the contractor and work is due to commence shortly. Thank you for your patience.
Posted by Bromley Council
at 12:58, Thursday 4 May 2023
-
We are in discussion with our contractor for a start date to complete this work. Thank you for your patience.
Posted by Bromley Council
at 12:33, Thursday 11 May 2023
-
This work is due to commence shortly. Thank you for your patience.
Posted by Bromley Council
at 10:41, Friday 19 May 2023
-
We are working with our Minor Works contractor to ensure this work is undertaken. Thank you for your patience.
Posted by Bromley Council
at 11:27, Thursday 1 June 2023
-
Appropriate action has been taken to resolve the issue.
State changed to: Fixed
Posted by Bromley Council
at 11:08, Thursday 13 July 2023