Road surface breaking up

Reported via mobile in the Road Defect category anonymously at 12:54, Mon 27 March 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 4363813.

Large area of road surface breaking up/ deteriorating

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 12:55, Mon 27 March 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 12:18, Wed 29 March 2023

  • Please bear with us. These works are outstanding with our Minor Works contractor and will be completed soon.

    Posted by Bromley Council at 16:32, Wed 10 May 2023

  • We are sorry that this work has not yet been completed. We are working with our Minor Works contractor in an effort to resolve this issue.

    Posted by Bromley Council at 12:42, Mon 26 June 2023

  • Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able

    Posted by Bromley Council at 20:09, Mon 11 September 2023

  • We are sorry that this work has not yet been completed. We are working with our Minor Works contractor in an effort to resolve this issue.

    Posted by Bromley Council at 15:55, Thu 28 September 2023

  • For information, the order for this repair remains outstanding within our contractor's planned schedule of work. Further arrangements are currently being undertaken to provide traffic management and/or the necessary specialist equipment in order to undertake the works.

    Posted by Bromley Council at 06:35, Wed 4 October 2023

  • Please bear with us. These works are still outstanding with our Minor Works contractor and will be completed soon.

    Posted by Bromley Council at 14:16, Fri 13 October 2023

  • Further works are necessary to resolve the issue and have been scheduled for action.

    Posted by Bromley Council at 07:55, Fri 20 October 2023

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 10:16, Thu 26 October 2023

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 15:27, Thu 26 October 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 15:07, Fri 27 October 2023

  • Please bear with us. These works are still outstanding with our Minor Works contractor and will be completed soon.

    Posted by Bromley Council at 14:08, Thu 4 January 2024

  • LBB apologises for the delay in action, here. We have instructed our Minor Works contractor to complete the repairs raised as soon as possible.

    Posted by Bromley Council at 11:20, Wed 21 February 2024

  • Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able

    Posted by Bromley Council at 11:28, Thu 29 February 2024

  • LBB apologises for the delay in action at this location. We are working with our Minor Works contractor to complete these repairs as soon as possible.

    Posted by Bromley Council at 13:41, Thu 28 March 2024

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 05:58, Thu 4 April 2024

This report is now closed to updates from the public. You can make a new report in the same location.