Poor quality, basically “USELESS” repair YET AGAIN.....

Reported via desktop in the Road Defect category anonymously at 11:43, Sat 12 August 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 4884585.

Please engage a COMPETENT contractor to undertake these most most basic of repairs....

This repair is NOT ACCEPTABLE and MUST be done PROPERLY and be able to withstand mounting by two+ tonne vehicles

As per attached 7am Saturday 12 August photos.....

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 11:44, Sat 12 August 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 09:00, Mon 14 August 2023

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 09:09, Tue 12 September 2023

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 11:03, Tue 24 October 2023

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 11:13, Wed 6 December 2023

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 12:49, Wed 10 January 2024

  • Our contractor has taken the appropriate action.

    State changed to: Fixed

    Posted by Bromley Council at 10:12, Tue 20 February 2024

  • Thank you for using FixMyStreet to report your concerns to Bromley.

    Posted by Bromley Council at 11:39, Thu 11 April 2024

  • Further works are necessary to resolve the issue and have been scheduled for action.

    State changed to: In progress

    Posted by Bromley Council at 09:23, Wed 19 June 2024

  • Thank you for using FixMyStreet to report your concerns to Bromley.

    State changed to: Fixed

    Posted by Bromley Council at 18:48, Tue 25 June 2024

  • Thank you for using FixMyStreet to report your concerns to Bromley.

    State changed to: Closed

    Posted by Bromley Council at 09:41, Wed 26 June 2024

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 10:01, Wed 26 June 2024