You can move around with your keyboard
plus
minus
left
right
Drop pin on the map to start a new report
space
Press space again to adjust the location
space
Start new report here Reposition report here
Back to all reports

Pothole 20cm by 15cm in centre of junction

Reported via Android in the Road Defect category anonymously at 14:05, Thu 30 November 2023

Sent to Bromley Council less than a minute later. FixMyStreet ref: 5269158.

Pothole is growing on junction of Cator Road and Leonard Road

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 14:05, Thu 30 November 2023

  • Our contractor is aware of this outstanding repairs and will be carried out shortly.

    Posted by Bromley Council at 11:51, Fri 1 December 2023

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 11:52, Fri 1 December 2023

  • This pothole has got significantly worse and is a hazard for cyclists as there is no where else to go due to 3-4 potholes in a small area and parked cars. Please can this be expedited, it is not safe.

    Posted anonymously at 14:08, Wednesday 3 January 2024

  • Thank you for your further comments regarding this issue. Bromley are aware of the significant volume of works raised and outstanding with our contractor and we are continuing to monitor and liaise with them over this outstanding schedule of works. Our Officers are not able to give precise timeframes to individual jobs at this moment but are continuing to undertake regular safety inspections and check any reported issues. We will continue to work with our contractor to ensure that all outstanding jobs are addressed as quickly as they are able

    State changed to: Closed

    Posted by Bromley Council at 12:07, Monday 8 January 2024

  • Please fix this pothole as soon as possible. It is almost impossible to avoid no matter what kind of vehicle you are in.

    Posted anonymously at 08:57, Thursday 11 January 2024

  • Traffic management is being arranged to carry out the work safely and should be carried out shortly. Thank you for your patience.

    Posted by Bromley Council at 12:29, Thursday 22 February 2024

  • This pothole is now so bad there are about 5 holes in close proximity and they’re getting very deep. It’s impossible to miss as a cyclist and will cause a cyclist to get thrown off their bike in a minute. This needs to be prioritised. It’s at an already very dangerous junction. An accident waiting to happen.

    Posted anonymously at 22:09, Wednesday 13 March 2024

  • Our contractor is organising the repairs with Traffic Management so that the repairs can be carried out safely. Thank you for your patience.

    Posted by Bromley Council at 09:32, Wednesday 20 March 2024

  • The issue has been re-attended and additional works completed. If the issue re-occurs please re-report via: https://fix.bromley.gov.uk

    State changed to: Fixed

    Posted by Bromley Council at 12:20, Tuesday 26 March 2024

This report is now closed to updates from the public. You can make a new report in the same location.