Delaminated oblong of road surface

Reported via desktop in the Road Defect category anonymously at 09:53, Sun 23 February 2025

Sent to Bromley Council less than a minute later. FixMyStreet ref: 7173742.

As per attached 8am Sunday 23 February photos….

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 09:53, Sun 23 February 2025

  • In need of attention

    Posted anonymously at 07:12, Mon 24 February 2025

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 07:39, Tue 25 February 2025

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 15:38, Thu 10 April 2025

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 20:47, Tue 20 May 2025

  • First reported eight seven days ago

    Posted anonymously at 07:56, Wed 21 May 2025

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 11:23, Thu 19 June 2025

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 09:43, Tue 5 August 2025

  • The order for this repair has been raised with the Council’s contractor and remains outstanding within their planned schedule of works.

    Please continue to bear with us. We anticipate an early resolution to this report from this point in time.

    Posted by Bromley Council at 10:49, Tue 12 August 2025

  • The remedial works are complete.

    State changed to: Fixed

    Posted by Bromley Council at 09:29, Wed 3 September 2025

  • The issue has been re-attended and additional works completed. If the issue re-occurs please re-report via: https://fix.bromley.gov.uk

    Posted by Bromley Council at 09:35, Wed 3 September 2025

This report is now closed to updates from the public. You can make a new report in the same location.