Large potholes

Reported via mobile in the Road Defect category anonymously at 21:10, Thursday 27 March 2025

Sent to Bromley Council less than a minute later. FixMyStreet ref: 7349636.

There are approximately 3/4 large potholes just after the roundabout heading towards Downe Road.

Updates

  • Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices

    State changed to: In progress

    Posted by Bromley Council at 21:11, Thursday 27 March 2025

  • In need of attention

    Posted anonymously at 06:32, Friday 28 March 2025

  • Our contractor has been notified to take the appropriate action.

    Posted by Bromley Council at 10:38, Monday 31 March 2025

  • Why are we still waiting for a fix on these half dozen holes. You highlighted them in white paint weeks ago, and that is fading now. Why is this section of road maintained so badly, if at all, and why having waited MONTHS for a fix, your repairs last all of 2 months, depending on the season? Only taxpayers money then?

    Posted anonymously at 16:14, Thursday 8 May 2025

  • We have requested a repair date from our contractor and await their response. Thank you for your patience in the meantime.

    Posted by Bromley Council at 10:03, Wednesday 21 May 2025

  • First reported fifty five days ago.

    Posted anonymously at 13:18, Wednesday 21 May 2025

  • And the wait goes on, how many damaged wheels, tyres, suspension parts because of the council and contractors intransigence, before we start on near fatalities in the cycling arena. Doing nothing has consequences!

    Posted anonymously at 14:20, Wednesday 21 May 2025

  • And the holes are generally failed repairs from the time before! Nevermind, it's only taxpayers money!

    Posted anonymously at 14:21, Wednesday 21 May 2025

  • I have noted they are getting progressively worse.

    Posted anonymously at 18:39, Wednesday 21 May 2025

  • Appropriate action has been taken to resolve the issue.

    State changed to: Fixed

    Posted by Bromley Council at 10:05, Thursday 22 May 2025

  • Further works are necessary to resolve the issue and have been scheduled for action.

    State changed to: In progress

    Posted by Bromley Council at 15:14, Thursday

Only the original reporter may leave updates. If you made the original report please log in to leave an update.