All 7 lights around the carpark facing the park not working
Reported via desktop in the Light Not Working category anonymously at 14:59, Mon 10 November 2025
Sent to Bromley Council less than a minute later. FixMyStreet ref: 8399564.
In the car park there are 7 lights not working, the whole of the grass side (x5) and both ends (x2) also the entrance access road lights
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 15:00, Mon 10 November 2025
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 09:27, Thu 18 December 2025
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 09:31, Thu 18 December 2025
-
Bromley Council are aware of this issue as it has either been brought to our attention already or we have existing job(s) within our schedule of works to address it. We will look to investigate and resolve the issue within our service standards: http://www.bromley.gov.uk/ fixservices Thank you once again for using ‘FixMyStreet’ to report this issue. If this problem persists, please provide further comments to the report.
State changed to: Duplicate
Posted by Bromley Council
at 10:45, Wednesday 21 January 2026
-
I met the contractor as he couldn't initially find the carpark, he was able to fix 4 lights in december. this week all the other lights on the other side of the carpark are not working. also and more importantly the 2 lights which provide the light for pedestrians to use the footpath from the swimming baths to the carpark are not working, this is a safety issue for pedestriains.
State changed to: Open
Posted by Richard SMITHSON at 12:42, Wednesday 21 January 2026
-
Your report is being investigated further. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 08:26, Thursday 22 January 2026
-
Our contractor has been notified to take the appropriate action.
Posted by Bromley Council
at 09:47, Wednesday 4 February 2026
Only the original reporter may leave updates. If you made the original report please log in to leave an update.